100 kW UPS Buying Guide: Sizing, Runtime & Quote Checklist
Use this checklist to turn a 100 kW UPS search into comparable supplier quotations. Start with the load you need to protect, then specify batteries, electrical scope and the capacity required during a failure or maintenance event.
What should you check before buying a 100 kW UPS?
A 100 kW UPS rating describes active output capacity, not backup duration. Check the separate kVA limit, input/output/bypass requirements, battery runtime at your load, and capacity remaining during the required failure state. Request an itemized installed quotation. Power Field Guide has no verified installed prices or live stock data.
Sources: Eaton UPS sizing guide ↗ · Schneider Electric Galaxy VS: Specifications for 480 V systems ↗
Start with the load you actually need to protect
Before requesting a 100 kW quotation, write down what the number means. Is it a measured peak, a planned IT load, a desired frame size, or an allowance for growth? These are different purchasing requirements. Label each figure with its source and date so vendors do not silently interpret an estimate as a measurement.
Eaton separates capacity from runtime in its sizing guidance and asks buyers to consider growth and redundancy. For this purchase, create a load schedule with current, committed and speculative additions in separate columns. Ask the project engineer to determine the design requirement; do not turn a generic percentage allowance into an approved equipment size.
- Identify protected equipment and the boundary of the UPS-backed distribution.
- Record measured kW and kVA, with the measurement period and unusual operating conditions.
- List future additions with an expected date and an owner who can confirm them.
- State the required service outcome during utility failure, maintenance and equipment failure.
Sources: Eaton UPS sizing guide ↗
Compare both kW and kVA, then check the electrical system
For an illustrative 90 kW load at power factor 0.90, apparent power is 90 ÷ 0.90 = 100 kVA. A hypothetical 100 kW / 100 kVA UPS is already at its kVA limit in this example. Its unused kW rating does not create apparent-power headroom.
Voltage is not a small-print preference. As one manufacturer example, Schneider Electric publishes a dedicated Galaxy VS specification table for 480 V systems with separate input, output and bypass information. Request the matching technical document for every quoted configuration, including any proposed transformer or switchgear. A voltage entry on a comparison card is insufficient installation documentation.
Passing these two checks is only a screening step. Growth, transient load, derating and redundancy still need design review; do not infer them from the unused kW figure.
| Proposed load | Apparent power required | Against a 100 kW / 100 kVA rating |
|---|---|---|
| 90 kW at PF 0.90 | 100 kVA | Within both limits; at the kVA limit |
| 90 kW at PF 0.80 | 112.5 kVA | Exceeds the kVA limit |
| 100 kW at PF 1.00 | 100 kVA | At both limits; no spare capacity by this arithmetic |
Sources: Schneider Electric Galaxy VS: Specifications for 480 V systems ↗ · Eaton: VA versus watts and power factor ↗
Understand what the 100 kW catalog filter actually means
Power Field Guide normalizes active and apparent output from the ENERGY STAR minimum tested configuration. A family that can be configured at 100 kW may appear under a different value when its minimum tested configuration is smaller. Model-name digits are not a substitute for the source rating.
At the September 12, 2026 catalog snapshot, the exact 100 kW filter returns one source record: EATON S3M100K, ID 4577047, with 100 kW active and 100 kVA apparent output. This is a description of the imported dataset, not a statement that only one 100 kW product exists. Certification data also does not establish stock, current commercial status or installed price.
Sources: ENERGY STAR Certified Uninterruptible Power Supplies dataset ↗ · ENERGY STAR AC UPS certification reporting fields ↗
Make suppliers answer the same purchasing questions
Send a short comparison sheet before accepting a proposal. Keep a column for unanswered items rather than treating silence as inclusion. If one vendor includes batteries and commissioning while another quotes only the power cabinet, the totals cannot yet be compared.
Use the table below as a request for evidence. It is an editorial procurement template, not a specification for any named UPS. Ask the person responsible for the design to approve the technical acceptance criteria before orders are placed.
| Item | Request from each bidder | Why it affects comparison |
|---|---|---|
| Configured output | Exact part numbers, installed capacity and kW/kVA ratings | Separates the supplied system from a family headline |
| Battery package | Exact cabinet and battery references plus runtime evidence | Makes runtime promises traceable |
| Electrical scope | Input/output/bypass requirements and included ancillaries | Exposes work outside the UPS cabinet |
| Resilience | Capacity remaining during the specified failure or service event | Defines what redundancy is intended to accomplish |
| Delivery and startup | Dated delivery commitment and commissioning scope | Separates shipment from an operational installation |
| Commercial exclusions | Installation, freight, tax, permits and service exclusions | Allows a complete project budget |
Treat runtime and operating cost as separate comparisons
Do not accept a battery count as a runtime commitment. Request a manufacturer runtime curve or written sizing output for the exact battery arrangement at the agreed load. Put the promised runtime and the conditions behind it in the same row of your comparison. The runtime guide explains how to review that evidence.
For operating costs, compare the same mode and expected load rather than choosing the highest advertised percentage. ENERGY STAR’s reporting template separates load-specific efficiency from weighted efficiency. Request the data needed for a site-specific loss estimate, then compare service scope, battery replacement assumptions and the installed quotation separately.
Sources: Eaton UPS sizing guide ↗ · ENERGY STAR AC UPS certification reporting fields ↗
Finish with a decision record you can defend
For each shortlisted system, record the evidence received, unresolved questions, responsible reviewer and the next decision. A proposal becomes easier to evaluate when a missing battery document has a named owner instead of disappearing into an email chain.
Before award, ask the selected supplier to reconcile its final bill of materials with the reviewed proposal. Keep the approved configuration and commissioning requirements with the purchase record. If a substitution appears later, route it back through the same review instead of relying on a similar-looking model name.
Common questions
Is a 100 kVA UPS the same as a 100 kW UPS?
Not necessarily. Compare the stated active-power and apparent-power limits separately. A hypothetical 90 kW load at 0.90 power factor is 100 kVA, but that conversion alone does not establish an acceptable design.
Why does the 100 kW filter show so few products?
The filter uses minimum tested active output from the imported ENERGY STAR records. It does not search every capacity a manufacturer family may support, and it is not a complete market inventory.
Sources: ENERGY STAR Certified Uninterruptible Power Supplies dataset ↗
How much does a 100 kW UPS cost installed?
Power Field Guide does not have verified installed prices. Obtain comparable quotations covering the exact UPS, batteries, electrical work, delivery, commissioning and service. A cabinet-only price cannot answer the installed-cost question.
How long will a 100 kW UPS run?
Its output rating does not determine runtime. Request the exact battery configuration and the manufacturer runtime evidence at your required load.
Sources: Eaton UPS sizing guide ↗
Sources and editorial scope
Published by Power Field Guide using the primary sources below and original procurement examples. Manufacturer and provider statements are attributed to their source. Examples are illustrative; this guide is not a site design or confirmation of equipment availability.
- Eaton UPS sizing guide ↗Checked 2026-10-23
- Schneider Electric Galaxy VS: Specifications for 480 V systems ↗Checked 2026-10-23
- ENERGY STAR Certified Uninterruptible Power Supplies dataset ↗Checked 2026-09-12
- ENERGY STAR UPS key product criteria ↗Checked 2026-09-12
- Eaton UPS battery runtime graphs ↗Checked 2026-09-12
- Eaton: VA versus watts and power factor ↗Checked 2026-10-23
- ENERGY STAR AC UPS certification reporting fields ↗Checked 2026-10-23